PropPin
High risk
  • Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 96.4%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2026 per the RERA filing.
Ghatkopar / VikhroliUpper-mid

Metro-1 anchor with Godrej's Vikhroli land bank next door.

Growth drivers:
Metro 1 interchange, Eastern Express Highway, corporate campuses.
Who buys here:
Families wanting east-side connectivity to BKC/Fort.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
MANSUKHLAL VELJI SENGHANI

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
Deole Bros

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51800048036
Status
New
Stage
Certificate Signed
Possession
June 2026
Construction
96.4% complete
Units sold
25 of 31

Similar projects in Kurla

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 19 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.