High risk
  • Litigation pending (3). MahaRERA's litigation disclosure lists 3 pending cases against this project.
  • Possession delayed ~2 yrs. Originally promised Mar 2025, now proposed Sept 2026 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2026 per the RERA filing.

Area guide

What it's like to buy in Borivali

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Kandivali / BorivaliMid-income

Self-sufficient Gujarati-dominated family belt beside the National Park.

Growth drivers:
Metro 2A/7, station upgrades, big-brand township launches.
Who buys here:
Families seeking space and community at sane prices.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
Polo Infra Developers Private Limited

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
Chirag S Rayani

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51800050616
Status
New
Stage
Certificate Signed
Possession
September 2026originally March 2025
Construction
54.5% complete
Units sold
12 of 35

Similar projects in Borivali

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.