High risk
  • Litigation pending (69). MahaRERA's litigation disclosure lists 69 pending cases against this project.
  • Mortgaged to a lender (₹700 Cr). MahaRERA's financial encumbrance declaration shows this project has ₹700 Cr secured against a lender — a lender's claim can outrank a buyer's if the promoter defaults.
  • Possession delayed ~5 yrs. Originally promised Dec 2023, now proposed Dec 2028 per the RERA filing.
  • 10 RERA complaints. 10 complaint records are disclosed against this project on MahaRERA.

Area guide

What it's like to buy in Ward E

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Mahalaxmi / TardeoUltra-luxury

Racecourse views and some of the city's tallest residences.

Growth drivers:
Scarcity, racecourse frontage, South Bombay prestige.
Who buys here:
Ultra-HNI trophy purchases.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
GODREJ RESIDENCY PRIVATE LIMITED

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
RUPALI D MANDE

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51900005216
Status
Ongoing
Stage
Certificate Signed
Possession
December 2028originally December 2023
Construction
58.7% complete
Units sold
170 of 227

Similar projects in Ward E

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.