High risk
  • Possession delayed ~8 yrs. Originally promised Jul 2018, now proposed Jul 2026 per the RERA filing.
  • Possession date passed. The proposed possession date (Jul 2026) has passed with construction at 97.4%.

Area guide

What it's like to buy in Mumbai City

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Parel / Dadar EastPremium

Mill-land towers around Maharashtra's busiest rail junction.

Growth drivers:
Hospital cluster jobs, central location, mill plot launches.
Who buys here:
South-Bombay workers wanting new construction.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
HEKS INFRASTRUCTURE & DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
SHAIKH & ASSOCIATES

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51900006034
Status
Ongoing
Stage
Certificate Signed
Possession
July 2026originally July 2018
Construction
97.4% complete
Units sold
21 of 24

Similar projects in Mumbai City

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.