  • 22 RERA complaints. 22 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (Sept 2019) has passed with construction at 95.2%.
Bandra East / BKC fringePremium

Offices-first district gaining residential towers on its edges.

Growth drivers:
BKC employment, Metro 2B/3, redevelopment of older colonies.
Who buys here:
BKC professionals wanting a walk-to-work life.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
MARVEL REALTORS AND DEVELOPERS LTD

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100002648
Status
Ongoing
Stage
Certificate Signed
Possession
September 2019originally September 2018
Construction
95.2% complete
Units sold
0 of 0

Similar projects in the area

Other MahaRERA-registered projects in the same district — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.