All RERA projects
MARVEL LANDMARKS PVT LTD
12 MahaRERA-tracked projects in Mumbai
12
Tracked projects
137
Complaint records
0
Recovery warrants
Computed only from official MahaRERA disclosures across this builder's (spelling-matched) portfolio.
Projects (12)
- 99 · A+MARVEL CERISE Bldg-APossession Dec 2017100% built3 complaints
- 97 · A+Marvel AurumPune CityPossession Jun 201878.9% built
- 97 · A+MARVEL CITRINE A BUILDINGPossession Dec 201790.9% built
- 87 · AMarvel FuegoHadapsarPossession Dec 201886.4% built5 complaints
- 87 · AMARVEL ZEPHYR BUILDING UPossession Jul 201890.9% built3 complaints
- 81 · AMarvel Ganga Sangria D,E BuildingMOHAMMADWADIPossession Mar 201899.4% built8 complaints
- 79 · BMarvel Ganga Sangria A,B,C BuildingMOHAMMADWADIPossession Dec 201976.8% built5 complaints
- 64 · CMarvel BrisaPune (M Corp.)Possession Mar 201991.2% built22 complaints
- 60 · CMarvel Ganga Sangria G,H,J BuildingMOHAMMADWADIPossession Dec 201995.2% built15 complaints
- 52 · CMARVEL CERISE BLDG B, C, DPossession Sept 201995.2% built22 complaints
- 43 · DMarvel Ganga Sangria K,L,M BuildingMOHAMMADWADIPossession Dec 202072.4% built14 complaints
- 27 · DMARVEL ISOLA J BUILDINGHaveliPossession Jun 202678.6% built40 complaints
Data from official MahaRERA public disclosures. Projects are grouped into one developer by the promoter name, the disclosed office and the MahaRERA filing account together, so differently spelt filings by one builder stay together and unrelated firms that merely share a common word do not (slug: marvel-landmarks). Scores are PropPin's transparent rule-based rating — every factor cites a disclosure. Not investment advice.