MARVEL CERISE BLDG B, C, D
by MARVEL REALTORS AND DEVELOPERS LTD
Sr No 58/2/1A/1A/1, 2/1A/3, 411014
- 8 appeals at MahaREAT. 8 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
- 22 RERA complaints. 22 complaint records are disclosed against this project on MahaRERA.
- Possession date passed. The proposed possession date (Sept 2019) has passed with construction at 95.2%.
Where it is · Sr No 58/2/1A/1A/1, 2/1A/3
Area guide
What it's like to buy in this area
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Offices-first district gaining residential towers on its edges.
- Growth drivers:
- BKC employment, Metro 2B/3, redevelopment of older colonies.
- Who buys here:
- BKC professionals wanting a walk-to-work life.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100002648
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- September 2019originally September 2018
- Construction
- 95.2% complete
- Units sold
- 0 of 0