All RERA projects
🏗️
Under construction
ASHTHAVINAYAK
MahaRERA P52100010511High risk
by UNITY GROUP BUILDERS AND DEVELOPERS
171 7, Tandulwadi, 413102
Post your property hereOwn or renting out a unit in ASHTHAVINAYAK? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Tandulwadi come to you.
Mar 2019
Possession
13.8%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Mar 2019) has passed with construction at 13.8%.
Promoter
Builder profile
UNITY GROUP BUILDERS AND DEVELOPERS
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100010511
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- March 2019
- Construction
- 13.8% complete
- Units sold
- 0 of 0
Similar projects in Tandulwadi
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
MATOSHREE RESIDENCY BUILDING D
TandulwadiPoss. December 2028
Matoshree Residency Building A
Tandulwadi90.9% builtPoss. December 2023
AAPLE GHAR TOWNSHIP A AND E WING
Tandulwadi90.9% builtPoss. March 2024
Matoshree Residency Building B
Tandulwadi81.8% builtPoss. December 2024
BHAGWAN COMPLEX A
Tandulwadi9.1% builtPoss. December 2026
Matoshree Residency Building C
Tandulwadi0% builtPoss. April 2027
BHAGWAN COMPLEX
Tandulwadi0% builtPoss. December 2024
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.