All RERA projects
🏗️
Under construction
TULIP SWAPNALOK
MahaRERA P52100011375High risk
660,661,662,663,666 AT MOSHI, Pimpri Chinchawad (M Corp.), 412105
Post your property hereOwn or renting out a unit in TULIP SWAPNALOK? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Pimpri Chinchawad (M Corp.) come to you.
Oct 2020
Possession
90.9%
Built
2
Complaints
0
Units
High risk
- Possession delayed ~3 yrs. Originally promised Dec 2017, now proposed Oct 2020 per the RERA filing.
- Possession date passed. The proposed possession date (Oct 2020) has passed with construction at 90.9%.
Promoter
Builder profile
Tulip Properties
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100011375
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- October 2020originally December 2017
- Construction
- 90.9% complete
- Units sold
- 0 of 0
Similar projects in Pimpri Chinchawad (M Corp.)
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
PAVAN
Pimpri Chinchawad (M Corp.)Poss. September 2027
Mahindra Citadel - Phase 5
Pimpri Chinchawad (M Corp.)Poss. August 2031
SILVER 9
Pimpri Chinchawad (M Corp.)100% builtPoss. December 2021
Ashirwad The Living B Wing
Pimpri Chinchawad (M Corp.)100% builtPoss. July 20181 complaint
Svasti Chandrasuman
Pimpri Chinchawad (M Corp.)100% builtPoss. August 2019
ICONIA Phase III
Pimpri Chinchawad (M Corp.)100% builtPoss. December 2022
SILVERLAND RESIDENCY PHASE-1
Pimpri Chinchawad (M Corp.)100% builtPoss. December 2021
SWASTIK SPIRA
Pimpri Chinchawad (M Corp.)100% builtPoss. March 2018
Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.