PropPin
🏗️
Under construction

ARV Newtown Phase II

MahaRERA P52100015904High risk

by Vedant Infracon

S no 14/1 14/2 14/3 14/4/14/5 14/6 14/7 15/4 and 16/3/3, Pisoli, 411028

Official record
Dec 2025
Possession
69.1%
Built
0
Complaints
0
Units
High risk
  • Litigation pending (2). MahaRERA's litigation disclosure lists 2 pending cases against this project.
  • Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 69.1%.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Dec 2025 per the RERA filing.

Area guide

What it's like to buy in Pisoli

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Vedant Infracon

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100015904
Status
New
Stage
Certificate Signed
Possession
December 2025
Construction
69.1% complete
Units sold
0 of 0

Similar projects in Pisoli

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.