Under construction
ARV Newtown Phase II
MahaRERA P52100015904High risk
S no 14/1 14/2 14/3 14/4/14/5 14/6 14/7 15/4 and 16/3/3, Pisoli, 411028
Post your property hereOwn or renting out a unit in ARV Newtown Phase II? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Pisoli come to you.
Dec 2025
Possession
69.1%
Built
0
Complaints
0
Units
High risk
- Litigation pending (2). MahaRERA's litigation disclosure lists 2 pending cases against this project.
- Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 69.1%.
- Promised amenities not started. Clubhouse is at 0% build with possession due Dec 2025 per the RERA filing.
Area guide
What it's like to buy in Pisoli
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
Vedant Infracon
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100015904
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2025
- Construction
- 69.1% complete
- Units sold
- 0 of 0
Similar projects in Pisoli
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Advika Phase IV-C
PisoliPoss. December 2030
EMERALD GREEN
PisoliPoss. August 2028
Prime Vista
PisoliPoss. December 2029
Prime Vista Row Houses
PisoliPoss. December 2029
GAGAN LAWISH PHASE 2
Pisoli100% builtPoss. December 2020
ATUR VALLY VISTA WING B
Pisoli95% builtPoss. December 2017
BROOKEFIELD WILLOWS
Pisoli90.9% builtPoss. December 20191 complaint
SUNSHINE HILLS PHASE-II A-5
Pisoli90.9% builtPoss. December 2023
Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.