PropPin
🏗️
Under construction

MELANGE RESIDENCES - PHASE III

MahaRERA P52100017090High risk

by RAMA SYNERGY SPACES

S. NO. 11 HISSA NO 1, 2 AND 3, S. NO. 37 HISSA NO 1, 3, 4 AND 5, Hinjawadi Phase III, 411057

Official record
Sept 2021
Possession
94.5%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Sept 2021) has passed with construction at 94.5%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2021 per the RERA filing.

Area guide

What it's like to buy in Hinjawadi Phase III

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
RAMA SYNERGY SPACES

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100017090
Status
New
Stage
Certificate Signed
Possession
September 2021
Construction
94.5% complete
Units sold
0 of 0

Similar projects in Hinjawadi Phase III

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.