Under construction
Building B2 Eon Homes
MahaRERA P52100048176Caution
by Hinjawadi Infradevelelopment Private Limited
Plot R-3/1 Part, Hinjawadi Phase III, 411057
Post your property hereOwn or renting out a unit in Building B2 Eon Homes? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Hinjawadi Phase III come to you.
Dec 2027
Possession
13.6%
Built
0
Complaints
183
Units
Caution
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.
Area guide
What it's like to buy in Hinjawadi Phase III
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
Hinjawadi Infradevelelopment Private Limited
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100048176
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2027
- Construction
- 13.6% complete
- Units sold
- 143 of 183
Similar projects in Hinjawadi Phase III
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
MELANGE RESIDENCES - PHASE III
Hinjawadi Phase III94.5% builtPoss. September 2021
MELANGE RESIDENCES - PHASE IV
Hinjawadi Phase III94.5% builtPoss. December 2022
MELANGE RESIDENCES - PHASE I
Hinjawadi Phase III91.8% builtPoss. December 20181 complaint
MELANGE RESIDENCES - PHASE II
Hinjawadi Phase III87.7% builtPoss. December 2020
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.