AVANI AAVAS
MahaRERA P52100017244High risk
by AVANI CORP
GAT NO 424, KALJEWADI, 412105
Post your property hereOwn or renting out a unit in AVANI AAVAS? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in KALJEWADI come to you.
Jun 2023
Possession
62.8%
Built
1
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Jun 2023) has passed with construction at 62.8%.
- Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Jun 2023 per the RERA filing.
Promoter
Builder profile
AVANI CORP
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100017244
- Status
- New
- Stage
- Certificate Signed
- Possession
- June 2023originally December 2022
- Construction
- 62.8% complete
- Units sold
- 0 of 0
Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.