PropPin
All RERA projects
🏗️
Under construction

Nature Green

MahaRERA P52100076828High risk

by Avani Construction

PLOT NO. A-19 + A-20, S. NO. 63/1A, APARAJITA SOCIETY, 411021

Official record
Apr 2027
Possession
0%
Built
0
Complaints
0
Units
High risk
  • Behind schedule. Possession is due Apr 2027 but construction is only at 0%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2027 per the RERA filing.

Promoter

Builder profile

Builder
Avani Construction

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100076828
Status
New
Stage
Certificate Signed
Possession
April 2027
Construction
0% complete
Units sold
0 of 0

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.