PropPin
All RERA projects
🏗️
Under construction

PRADHAN MANTRI AWAS YOJANA- CHARHOLI

MahaRERA P52100017367High risk

by PIMPRI CHINCHWAD MUNICIPAL CORPORATION

New Survey no 108 and Old Survey no 409, Charholi, 412105

Official record
Dec 2023
Possession
64.5%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2023) has passed with construction at 64.5%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2023 per the RERA filing.

Promoter

Builder profile

Builder
PIMPRI CHINCHWAD MUNICIPAL CORPORATION

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100017367
Status
New
Stage
Certificate Signed
Possession
December 2023originally December 2022
Construction
64.5% complete
Units sold
0 of 0

Similar projects in Charholi

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.