Caution
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.

Promoter

Builder profile

Builder
M/s Malhar Promoters and Land Developers LLP

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
M s Manthan Architects

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P52100051577
Status
New
Stage
Certificate Signed
Possession
December 2027originally December 2026
Construction
42.7% complete
Units sold
58 of 169

Similar projects in Charholi

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.