HILL CREST

MahaRERA P52100018833High risk

by NISARG GROUP

SURVEY NO. 97, HISSA NO. 1A/1A/1, RAVET, 412101

Official record
Dec 2023
Possession
71.4%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2023) has passed with construction at 71.4%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2023 per the RERA filing.

Promoter

Builder profile

Builder
NISARG GROUP

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100018833
Status
New
Stage
Certificate Signed
Possession
December 2023
Construction
71.4% complete
Units sold
0 of 0

Similar projects in RAVET

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.