Under construction
Kingston Greens Phase 1
MahaRERA P52100019471High risk
S. No. 18/1B/1/1, 18/1A, Haveli, 411028
Post your property hereOwn or renting out a unit in Kingston Greens Phase 1? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Haveli come to you.
Jun 2027
Possession
60.5%
Built
0
Complaints
339
Units
High risk
- Mortgaged to a lender (₹20 Cr). MahaRERA's financial encumbrance declaration shows this project has ₹20 Cr secured against a lender — a lender's claim can outrank a buyer's if the promoter defaults.
- Possession delayed ~1 yr. Originally promised Dec 2025, now proposed Jun 2027 per the RERA filing.
- Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Jun 2027 per the RERA filing.
Area guide
What it's like to buy in Haveli
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
Vedant Developments
View the promoter’s full developer profile and other projects under the same builder group.
Architect
Design profile
VILAS TARWADI
Browse other projects associated with this architect to compare design and delivery patterns.
Official RERA facts
- Registration
- P52100019471
- Status
- New
- Stage
- Certificate Signed
- Possession
- June 2027originally December 2025
- Construction
- 60.5% complete
- Units sold
- 178 of 339
Similar projects in Haveli
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Audumbar Nest A1 A2 and B Building
HaveliPoss. December 2027
Skyi Wild Woods Phase I
HaveliPoss. July 2027
Ellora Enclave
HaveliPoss. July 2028
ASHIRWAD SAPPHIRE
HaveliPoss. December 2029
MAGNUS
HaveliPoss. March 2029
SIGMA CENTURIA PHASE II
HaveliPoss. December 2030
Oxygreens
HaveliPoss. December 2028
Kaka Nano Homes
HaveliPoss. December 2026
Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.