Godrej Park Greens
MahaRERA P52100019639High risk
by Godrej Skyline Developers Limited
Plot 1 of Survey nos 11/1A, 12/1, 12/2/1, 12/2/2, 12/2/3, 13/1B part and 13/2, Village Mamurdi, Mamurdi, 412101
Post your property hereOwn or renting out a unit in Godrej Park Greens? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Mamurdi come to you.
Mar 2028
Possession
80%
Built
67
Complaints
1,210
Units
High risk
- Possession delayed ~4 yrs. Originally promised Mar 2024, now proposed Mar 2028 per the RERA filing.
- 67 RERA complaints. 67 complaint records are disclosed against this project on MahaRERA.
Promoter
Builder profile
Godrej Skyline Developers Limited
View the promoter’s full developer profile and other projects under the same builder group.
Architect
Design profile
Studio 30 Architects and Planners
Browse other projects associated with this architect to compare design and delivery patterns.
Official RERA facts
- Registration
- P52100019639
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2028originally March 2024
- Construction
- 80% complete
- Units sold
- 1193 of 1210
Similar projects in Mamurdi
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
JEFRO KINGSFORT
MamurdiPoss. December 2030
My Home Sanctuary Phase I
MamurdiPoss. December 2031
Millennium Amara Phase 2
MamurdiPoss. December 2029
RK AMOR
MamurdiPoss. March 2030
ICONIA PHASE IV
Mamurdi100% builtPoss. December 2022
Millennium Amara
Mamurdi80.5% builtPoss. March 2028
ESHAN CULTURE
Mamurdi67.3% builtPoss. February 2024
Emerald Heights
Mamurdi60.7% builtPoss. December 2027
Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.