FOREST GROVE AT GODREJ PARK GREENS

MahaRERA P52100023129High risk

by Godrej Skyline Developers Limited

PLOT NO 1 BEARING S NO 10/1A/3, 10/1B, 11/1A, 11/2A PART, 11/3, 11/4 PART, 11/4/2, 11/1B, 12/1, 12/2/1, 12/2/2, 12/2/3, 13/2, 13/1B PART PLOT 01 IN VILLAGE MAMURDI, MAMURDI VILLAGE, 412101

Official record
Sept 2027
Possession
70.9%
Built
37
Complaints
1,139
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Mar 2025, now proposed Sept 2027 per the RERA filing.
  • 37 RERA complaints. 37 complaint records are disclosed against this project on MahaRERA.

Promoter

Builder profile

Builder
Godrej Skyline Developers Limited

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
Studio 30 Architects and Planners

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52100023129
Status
New
Stage
Certificate Signed
Possession
September 2027originally March 2025
Construction
70.9% complete
Units sold
1125 of 1139

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.