VANTAGE CAPITAL

MahaRERA P52100025551Caution

by VINODE WAKADKAR INFRASTRUCTURE

SR. NO. 263/1/4, 264/2A, 264/2B, 264/1A,/2, 264/1B/2, HINJEWADI, 411057

Official record
Mar 2027
Possession
80.9%
Built
0
Complaints
395
Units
Caution
  • Possession delayed ~2 yrs. Originally promised Sept 2024, now proposed Mar 2027 per the RERA filing.

Promoter

Builder profile

Builder
VINODE WAKADKAR INFRASTRUCTURE

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100025551
Status
New
Stage
Certificate Signed
Possession
March 2027originally September 2024
Construction
80.9% complete
Units sold
129 of 395

Similar projects in HINJEWADI

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.