PRIMEROSE
MahaRERA P52100051551High risk
SR NO 36 H.NO. 7/1,7/2,7/3/1,7/3/1,,7/3/2,7/4,5/2, AMBEGAON BK, 411046
Post your property hereOwn or renting out a unit in PRIMEROSE? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in AMBEGAON BK come to you.
Mar 2027
Possession
49.9%
Built
0
Complaints
174
Units
High risk
- Behind schedule. Possession is due Mar 2027 but construction is only at 49.9%.
- Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Mar 2027 per the RERA filing.
Promoter
Builder profile
GURUKRUPA DEVELOPERS
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100051551
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2027originally March 2026
- Construction
- 49.9% complete
- Units sold
- 105 of 174
Similar projects in AMBEGAON BK
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
VARAD DWARKA
AMBEGAON BKPoss. December 2028
VIDYANNAD
AMBEGAON BK90.9% builtPoss. March 2023
SHREE SADGURU CHHAYA
AMBEGAON BK81.8% builtPoss. December 2023
SAI GANESH
AMBEGAON BK81.8% builtPoss. March 2026
YASHODA COMPLEX
AMBEGAON BK81.4% builtPoss. December 2024
VASTUDEEP AVENUE
AMBEGAON BK77.5% builtPoss. August 2026
ADISHREE
AMBEGAON BK65.9% builtPoss. September 2023
REELICON KIAN
AMBEGAON BK54.5% builtPoss. December 2019
Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.