PropPin
🏗️
Under construction

NYATI EMERALD III

MahaRERA P52100055066High risk

by NYATI BUILDERS PRIVATE LIMITED

SURVEY NO. 55/2(P), 55/2/1+2, 55/4/1+2,55/4/4 TO 8, 55/4/10 TO 38, 55/4/40 TO 49, 55/4/51 TO 61, 55/4/63, 55/4/67 TO 73, 55/4/76+77, 55/4/78(P), 55/4/78/10+11, 55/4/79. BANER, PUNE, BANER, 411045

Official record
Aug 2028
Possession
56.1%
Built
1
Complaints
290
Units
High risk
  • Litigation pending (8). MahaRERA's litigation disclosure lists 8 pending cases against this project.
  • Mortgaged to a lender (₹270 Cr). MahaRERA's financial encumbrance declaration shows this project has ₹270 Cr secured against a lender — a lender's claim can outrank a buyer's if the promoter defaults.

Area guide

What it's like to buy in BANER

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
NYATI BUILDERS PRIVATE LIMITED

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
Milind Patil

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52100055066
Status
New
Stage
Certificate Signed
Possession
August 2028
Construction
56.1% complete
Units sold
163 of 290

Similar projects in BANER

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.