  • Possession delayed ~2 yrs. Originally promised Dec 2024, now proposed Nov 2026 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Nov 2026 per the RERA filing.
Juhu / Vile Parle WestUltra-luxury

Beachside bungalows and low-rise society redevelopments.

Growth drivers:
Beach frontage, airport access, redevelopment of ageing societies.
Who buys here:
Established business families, film industry.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
Sahyadri Builders and Developers

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52700003940
Status
Ongoing
Stage
Certificate Signed
Possession
November 2026originally December 2024
Construction
69.8% complete
Units sold
0 of 0

Similar projects in WAI

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.