All RERA projects
🏗️
Under construction
Anandvan Phase 1
MahaRERA P52700007067High risk
by SAHYADRI BUILDERS & DEVELOPERS
Survey No 605 H No 1, WAI, 412803
Post your property hereOwn or renting out a unit in Anandvan Phase 1? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in WAI come to you.
Nov 2026
Possession
86.4%
Built
0
Complaints
0
Units
High risk
- Possession delayed ~2 yrs. Originally promised Dec 2024, now proposed Nov 2026 per the RERA filing.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Nov 2026 per the RERA filing.
Promoter
Builder profile
SAHYADRI BUILDERS & DEVELOPERS
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52700007067
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- November 2026originally December 2024
- Construction
- 86.4% complete
- Units sold
- 0 of 0
Similar projects in WAI
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
HEERA PALACE
WAI81.8% builtPoss. July 2023
OMKARS TARANGAN
WAI81.1% builtPoss. March 2027
Anandvan Phase II
WAI69.8% builtPoss. November 2026
MEGHDOOT HEIGHTS
WAI67.5% builtPoss. October 2026
VALLABH PRASAD HEIGHTS
WAI46.8% builtPoss. December 2028
INDRAJA PRIDE
WAI9.1% builtPoss. December 2026
Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.