High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2019, now proposed Oct 2021 per the RERA filing.
  • Possession date passed. The proposed possession date (Oct 2021) has passed with construction at 39.8%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Oct 2021 per the RERA filing.
GoregaonUpper-mid

Film City flank with large integrated townships on both flanks.

Growth drivers:
Oberoi/NESCO belt, Metro 7, Western Express Highway offices.
Who buys here:
Upgraders wanting township amenities without Powai prices.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
VIJAY DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52700009574
Status
Ongoing
Stage
Certificate Signed
Possession
October 2021originally December 2019
Construction
39.8% complete
Units sold
0 of 0

Similar projects in Satara

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.