Under construction
Navkar Mahalaxmi Enclave
MahaRERA P52800007452High risk
123, Hissa No 2/103. 2/106, 2/109, Plot No 9,10,11, Khedshi, 415639
Post your property hereOwn or renting out a unit in Navkar Mahalaxmi Enclave? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Khedshi come to you.
Dec 2018
Possession
84.5%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Dec 2018) has passed with construction at 84.5%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2018 per the RERA filing.
Area guide
What it's like to buy in Khedshi
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
Navkar Developers
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52800007452
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2018
- Construction
- 84.5% complete
- Units sold
- 0 of 0
Similar projects in Khedshi
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Swarupa Residency
Khedshi90.9% builtPoss. November 2018
Pushpendra City- Mahalakshmi Enclave
Khedshi90.9% builtPoss. June 2022
SUMUKHAY RESIDENCY
Khedshi90.9% builtPoss. December 2024
Pushpendra City- Mahalakshmi Presidency
Khedshi90.9% builtPoss. June 2022
Pushpendra City - Sector 10
Khedshi83.6% builtPoss. June 2028
ANANYA
Khedshi81.8% builtPoss. August 2024
SADGURU ASHISH PHAZE II
Khedshi63.6% builtPoss. December 2025
SADGURU ASHISH
Khedshi63.6% builtPoss. March 2025
Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.