Mango Holiday Village Guhagar Bungalow No 42 and 93
MahaRERA P52800020526High risk
Survey No 6.1.1 and 6.1.2, Kirtanwadi, 415703
Post your property hereOwn or renting out a unit in Mango Holiday Village Guhagar Bungalow No 42 and 93? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Kirtanwadi come to you.
Apr 2022
Possession
63.6%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Apr 2022) has passed with construction at 63.6%.
- Promised amenities not started. Clubhouse is at 0% build with possession due Apr 2022 per the RERA filing.
Promoter
Builder profile
Samir Shrinivas Kale
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52800020526
- Status
- New
- Stage
- Certificate Signed
- Possession
- April 2022
- Construction
- 63.6% complete
- Units sold
- 0 of 0
Similar projects in Kirtanwadi
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Mango Holiday Village Guhagar - Bungalow No 27
Kirtanwadi81.8% builtPoss. October 2023
Mango Holiday Village, Guhagar - Bungalow No 6
Kirtanwadi81.8% builtPoss. December 2022
SIDDHAKALA SWAPNAPURTI
Kirtanwadi64.3% builtPoss. December 2027
Mango Holiday Village Guhagar - Bungalow No 94
Kirtanwadi63.6% builtPoss. November 2023
Mango Holiday Village Guhagar Bungalow No 88
Kirtanwadi63.6% builtPoss. March 2024
Mango Holiday Village Guhagar Bungalow No 100
Kirtanwadi63.6% builtPoss. March 2024
Mango Holiday Village Guhagar Bungalow No 106
Kirtanwadi63.6% builtPoss. March 2024
Mango Holiday Village Guhagar Bungalow No 56
Kirtanwadi63.6% builtPoss. December 2024
Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.