Mango Holiday Village Guhagar Bungalow No 95

MahaRERA P52800032945High risk

by Samir Shrinivas Kale

Survey No 6.1.1 and 6.1.2, Kirtanwadi, 415703

Official record
Nov 2023
Possession
63.6%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Nov 2023) has passed with construction at 63.6%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Nov 2023 per the RERA filing.

Promoter

Builder profile

Builder
Samir Shrinivas Kale

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52800032945
Status
New
Stage
Certificate Signed
Possession
November 2023
Construction
63.6% complete
Units sold
0 of 0

Similar projects in Kirtanwadi

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.