SANSKRUTI PARK

MahaRERA P52900001092High risk

by SANSKRUTI INFRASTRUCTURE

Survey No 253/18/9, 253/18/10, 253/18/11, Malwan (M Cl), 416606

Official record
Dec 2021
Possession
62.7%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2019, now proposed Dec 2021 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2021) has passed with construction at 62.7%.

Promoter

Builder profile

Builder
SANSKRUTI INFRASTRUCTURE

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52900001092
Status
Ongoing
Stage
Certificate Signed
Possession
December 2021originally December 2019
Construction
62.7% complete
Units sold
0 of 0

Similar projects in Malwan (M Cl)

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.