High risk
  • Possession delayed ~3 yrs. Originally promised Dec 2017, now proposed Oct 2020 per the RERA filing.
  • Possession date passed. The proposed possession date (Oct 2020) has passed with construction at 51.4%.

Promoter

Builder profile

Builder
Samarth Developers

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52900006080
Status
Ongoing
Stage
Certificate Signed
Possession
October 2020originally December 2017
Construction
51.4% complete
Units sold
0 of 0