PropPin
🏗️
Under construction

NAVKAR CITY PHASE II PART I

MahaRERA P99000009437High risk

by Navkar Estate and Homes Pvt Ltd

Survey No 332 Hissa no 7 8 and Survey No 333 hissa no 1 and 2, naigaon, 401208

Official record
Dec 2021
Possession
89.9%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2021) has passed with construction at 89.9%.
  • Promised amenities not started. Sports / Jogging is at 0% build with possession due Dec 2021 per the RERA filing.

Area guide

What it's like to buy in naigaon

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Vasai–VirarValue

The western line's volume market — dense affordable towers past Mira Road.

Growth drivers:
Suburban rail quadrupling, coastal-road extensions, MMR's biggest affordable pipeline.
Who buys here:
Budget-first buyers who commute the western line.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
Navkar Estate and Homes Pvt Ltd

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P99000009437
Status
Ongoing
Stage
Certificate Signed
Possession
December 2021
Construction
89.9% complete
Units sold
0 of 0

Similar projects in naigaon

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.