Under construction
Navkar City Phase III Part 1
MahaRERA P99000011641High risk
by Navkar Estate and Homes Pvt Ltd
Survey No 224 Hissa No 1, Vasai-Virar City (M Corp), 401208
Post your property hereOwn or renting out a unit in Navkar City Phase III Part 1? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Vasai-Virar City (M Corp) come to you.
Nov 2022
Possession
89.5%
Built
0
Complaints
0
Units
High risk
- Possession delayed ~1 yr. Originally promised Jun 2021, now proposed Nov 2022 per the RERA filing.
- Possession date passed. The proposed possession date (Nov 2022) has passed with construction at 89.5%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Nov 2022 per the RERA filing.
Area guide
What it's like to buy in Vasai-Virar City (M Corp)
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
Navkar Estate and Homes Pvt Ltd
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P99000011641
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- November 2022originally June 2021
- Construction
- 89.5% complete
- Units sold
- 0 of 0
Similar projects in Vasai-Virar City (M Corp)
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Musavvir Residency
Vasai-Virar City (M Corp)Poss. December 2030
VIDYA APARTMENT
Vasai-Virar City (M Corp)Poss. March 2028
SHAIKH RESIDENCY
Vasai-Virar City (M Corp)Poss. March 2030
Flora (Building no 07 - Wing A)
Vasai-Virar City (M Corp)Poss. December 2028
Dharti 5
Vasai-Virar City (M Corp)Poss. December 2028
MUNISH SMRITI
Vasai-Virar City (M Corp)100% builtPoss. December 2020
GALAXY APARTMENT
Vasai-Virar City (M Corp)90.9% builtPoss. December 2023
MAITRY POOJA BUILDING NO.3
Vasai-Virar City (M Corp)90.9% builtPoss. December 2021
Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.