High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2025, now proposed Dec 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.
Vasai–VirarValue

The western line's volume market — dense affordable towers past Mira Road.

Growth drivers:
Suburban rail quadrupling, coastal-road extensions, MMR's biggest affordable pipeline.
Who buys here:
Budget-first buyers who commute the western line.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
SHREE KRISHNA BUILDCON

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
ABHAY RAUT

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P99000034992
Status
New
Stage
Certificate Signed
Possession
December 2027originally December 2025
Construction
47.2% complete
Units sold
159 of 315

Similar projects in NAIGAON EAST

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.