- Possession delayed ~3 yrs. Originally promised Dec 2019, now proposed Dec 2022 per the RERA filing.
- Possession date passed. The proposed possession date (Dec 2022) has passed with construction at 62.7%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2022 per the RERA filing.
Where it is · 157,158,131, Ward ABCD
Area guide
What it's like to buy in Ward ABCD
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Mill-land towers around Maharashtra's busiest rail junction.
- Growth drivers:
- Hospital cluster jobs, central location, mill plot launches.
- Who buys here:
- South-Bombay workers wanting new construction.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51900005991
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2022originally December 2019
- Construction
- 62.7% complete
- Units sold
- 0 of 0
Similar projects in Ward ABCD
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Ward ABCD compares.
In Ward ABCD
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.