High risk
  • Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 85%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2025 per the RERA filing.
Satellite view of this address

Where it is · C.S.No.2113/K Plot No. 13 and 14, Kasaba Karveer Ruikar Colony Nimbalkar Colony

Area guide

What it's like to buy in Kasaba Karveer Ruikar Colony…

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
DESHPANDE INFRA

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
Elefant Architecture

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P53000050821
Status
New
Stage
Certificate Signed
Possession
December 2025
Construction
85% complete
Units sold
21 of 24

Keep exploring

Where this project sits, who built it, and how Kasaba Karveer Ruikar Colony Nimbalkar Colony compares.

Data sourced from the official MahaRERA portal; complaints last synced 16 Sept 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.