A Z LANDMARK

MahaRERA P52000027742High risk

by A Z REALTY

SURVEY NO 168 PLOT NO 48, KARJAT, 410101

Official record
Jun 2027
Possession
73.6%
Built
0
Complaints
22
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Jun 2023, now proposed Jun 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2027 per the RERA filing.

Promoter

Builder profile

Builder
A Z REALTY

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
HORIZON CONSULTANCY

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52000027742
Status
New
Stage
Certificate Signed
Possession
June 2027originally June 2023
Construction
73.6% complete
Units sold
7 of 22

Similar projects in KARJAT

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.