  • Possession delayed ~2 yrs. Originally promised Mar 2026, now proposed Sept 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2027 per the RERA filing.

Promoter

Builder profile

Builder
SHREENATH ENTERPRISES

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
DHARM YADAV

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P99000026724
Status
New
Stage
Certificate Signed
Possession
September 2027originally March 2026
Construction
81.8% complete
Units sold
30 of 62

Similar projects in UMROLI

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.