High risk
  • Behind schedule. Possession is due Dec 2026 but construction is only at 31.1%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Promoter

Builder profile

Builder
SHAH AND DASWANI

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
Abhay D Raut

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P99000048005
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2025
Construction
31.1% complete
Units sold
12 of 23

Similar projects in Virar West

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.