  • Possession delayed ~1 yr. Originally promised Dec 2026, now proposed Apr 2028 per the RERA filing.
Satellite view of this address

Where it is · 458 2/3/B, SUPALWADI STOP

Promoter

Builder profile

Builder
YASHRAJ ENTERPRISES

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
KISHAN NARSI PATEL

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P52800031948
Status
New
Stage
Certificate Signed
Possession
April 2028originally December 2026
Construction
70.3% complete
Units sold
50 of 106