- Possession delayed ~2 yrs. Originally promised Mar 2020, now proposed Mar 2022 per the RERA filing.
- Possession date passed. The proposed possession date (Mar 2022) has passed with construction at 90.9%.
Where it is · PLOT NO 4, 5 CTS NO 15847 171 , 172, Aurangabad (M Corp.)
Area guide
What it's like to buy in Aurangabad (M Corp.)
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51500003981
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- March 2022originally March 2020
- Construction
- 90.9% complete
- Units sold
- 0 of 0
Similar projects in Aurangabad (M Corp.)
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Aurangabad (M Corp.) compares.
In Aurangabad (M Corp.)
The developer
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.