AHILYA
151, DADAR WEST, 400028
- Possession delayed ~6 yrs. Originally promised Jan 2021, now proposed Apr 2027 per the RERA filing.
- Behind schedule. Possession is due Apr 2027 but construction is only at 0%.
Where it is · 151, DADAR WEST
Area guide
What it's like to buy in DADAR WEST
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P51900019882
- Status
- New
- Stage
- Certificate Signed
- Possession
- April 2027originally January 2021
- Construction
- 0% complete
- Units sold
- 9 of 24
Similar projects in DADAR WEST
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how DADAR WEST compares.
In DADAR WEST
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.