Under construction
AMI PARK
MahaRERA P53100045377High risk
by NEXON INFRA
PLOT NO. 10, RAMKRISHNA PARAMHANS SOCIETY, 416416
Post your property hereOwn or renting out a unit in AMI PARK? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in RAMKRISHNA PARAMHANS SOCIETY come to you.
Dec 2024
Possession
63.5%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Dec 2024) has passed with construction at 63.5%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2024 per the RERA filing.
Satellite view of this address
Where it is · PLOT NO. 10, RAMKRISHNA PARAMHANS SOCIETY
Promoter
Builder profile
NEXON INFRA
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Architect
Design profile
ASHISH J CHINCHAWADE
Browse other projects associated with this architect to compare design and delivery patterns.
No other projects are linked to this architect yet.
Official RERA facts
- Registration
- P53100045377
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2024
- Construction
- 63.5% complete
- Units sold
- 0 of 0
Keep exploring
Where this project sits, who built it, and how RAMKRISHNA PARAMHANS SOCIETY compares.
In RAMKRISHNA PARAMHANS SOCIETY
The developer
Data sourced from the official MahaRERA portal; complaints last synced 17 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.