High risk
  • Possession delayed ~3 yrs. Originally promised Jul 2023, now proposed Jul 2026 per the RERA filing.
  • Possession date passed. The proposed possession date (Jul 2026) has passed with construction at 78.2%.
Satellite view of this address

Where it is · CTS NO. 18762, Silk Mill Colony

Promoter

Builder profile

Builder
Shree Amrut Sai Developer Pvt.Ltd

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
Ganesh Shriram Mharolkar

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P51500011307
Status
Ongoing
Stage
Certificate Signed
Possession
July 2026originally July 2023
Construction
78.2% complete
Units sold
224 of 304

Keep exploring

Where this project sits, who built it, and how Silk Mill Colony compares.

Data sourced from the official MahaRERA portal; complaints last synced 11 Sept 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.