High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2024, now proposed Mar 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2027 per the RERA filing.
Satellite view of this address

Where it is · Survey No 605 H No 1, WAI

Promoter

Builder profile

Builder
SAHYADRI BUILDERS & DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52700007067
Status
Ongoing
Stage
Certificate Signed
Possession
March 2027originally December 2024
Construction
86.4% complete
Units sold
0 of 0

Similar projects in WAI

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how WAI compares.

Data sourced from the official MahaRERA portal; complaints last synced 24 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.