Official record
Aug 2027
Possession
24.7%
Built
0
Complaints
223
Units
Caution
  • Behind schedule. Possession is due Aug 2027 but construction is only at 24.7%.
Satellite view of this address

Where it is · S.No. 331/A/1, 331B, CTS.No. 3499,3499/1,3502/A,3502/B,3500/1,3503,3503/1,3503/2,3503/3,3504, Jaystambha

Area guide

What it's like to buy in Jaystambha

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Deepak Yashwant Salvi

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52800051050
Status
New
Stage
Certificate Signed
Possession
August 2027originally April 2027
Construction
24.7% complete
Units sold
100 of 223