High risk
  • Possession delayed ~6 yrs. Originally promised Dec 2020, now proposed Apr 2027 per the RERA filing.
  • Behind schedule. Possession is due Apr 2027 but construction is only at 43.6%.
Satellite view of this address

Where it is · 2105/1, Waghmodewadi

Promoter

Builder profile

Builder
Ghaisas Developers LLP

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
SM Landage

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P52700019397
Status
Ongoing
Stage
Certificate Signed
Possession
April 2027originally December 2020
Construction
43.6% complete
Units sold
15 of 18

Keep exploring

Where this project sits, who built it, and how Waghmodewadi compares.

Data sourced from the official MahaRERA portal; complaints last synced 17 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.