High risk
  • Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Oct 2027 per the RERA filing.
Satellite view of this address

Where it is · CS no- 2/103 and F.P. No - 765(B), Mumbai City

Area guide

What it's like to buy in Mumbai City

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Lower Parel / WorliUltra-luxury

Mill-land skyscraper district — corporate HQs, five-stars and sea-view towers.

Growth drivers:
Coastal Road and Sea Link access, premium office stock, Worli sea-face cachet.
Who buys here:
CXOs, HNIs and investors chasing trophy addresses.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
BUILDARCH SAKURA

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
ANIL RAMAKANT PATIL RAMAKANT PATIL

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P51900055573
Status
New
Stage
Certificate Signed
Possession
October 2027originally December 2026
Construction
68.2% complete
Units sold
8 of 28

Similar projects in Mumbai City

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Mumbai City compares.

Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.