Construction of 584 EWS flat under PMAY on kh no. 395, 396, 397, 398, 399 and 400 mouza Bhandara

MahaRERA P50600055513High risk

by MHADA (Nagpur board)

Sr no 395, 396, 397, 398, 399 and 400 mouza pinglalai bhandara, ITI Collage Back Side, 441904

Official record
Apr 2027
Possession
4.8%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2024, now proposed Apr 2027 per the RERA filing.
  • Behind schedule. Possession is due Apr 2027 but construction is only at 4.8%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2027 per the RERA filing.
Satellite view of this address

Where it is · Sr no 395, 396, 397, 398, 399 and 400 mouza pinglalai bhandara, ITI Collage Back Side

Area guide

What it's like to buy in ITI Collage Back Side

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
MHADA (Nagpur board)

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P50600055513
Status
New
Stage
Certificate Signed
Possession
April 2027originally December 2024
Construction
4.8% complete
Units sold
0 of 0

Keep exploring

Where this project sits, who built it, and how ITI Collage Back Side compares.

Data sourced from the official MahaRERA portal; complaints last synced 16 Sept 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.