High risk
  • Possession date passed. The proposed possession date (Oct 2019) has passed with construction at 81.8%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Oct 2019 per the RERA filing.
Satellite view of this address

Where it is · Sr no 26 Hissa no 2 2 1 1 19

Area guide

What it's like to buy in this area

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

GoregaonUpper-mid

Film City flank with large integrated townships on both flanks.

Growth drivers:
Oberoi/NESCO belt, Metro 7, Western Express Highway offices.
Who buys here:
Upgraders wanting township amenities without Powai prices.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
VALSAMMA MAMACHAN

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100010483
Status
Ongoing
Stage
Certificate Signed
Possession
October 2019
Construction
81.8% complete
Units sold
0 of 0

Keep exploring

Where this project sits, who built it, and how the district compares.

Data sourced from the official MahaRERA portal; complaints last synced 17 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.